Issue - meetings

2024-25 Capital Outturn

Meeting: 12/05/2025 - Corporate Policy and Resources Committee (Item 55)

55 2024-25 Capital Outturn pdf icon PDF 477 KB

Committee is asked to acknowledge the Capital Outturn of £463k projected overspend against the Council’s Estimated Capital Programme for 2024-25, as at 31 March 2025.

Additional documents:

Decision:

The Committee resolved to acknowledge the Capital Outturn of £463k projected overspend against the Council’s Estimated Capital Programme for 2024/25 as at 31 March 2025.

Minutes:

The Committee queried the £150k that had been budgeted for the former Decathlon Unit in the Elmsleigh Centre that was no longer needed due to the space being used as a Surrey County Council Library. Officers were asked to consider using this amount for the relocation of the museum.

 

The £500k overspend on the Eclipse Leisure Centre was queried and further details were requested by the Committee.

 

The Committee resolved to acknowledge the Capital Outturn of £463k projected overspend against the Council’s Estimated Capital Programme for 2024/25 as at 31 March 2025.