Issue - meetings

Thameside House Construction Budget approval

Meeting: 19/07/2018 - Council (Item 176)

Thameside House Construction Budget approval

Minutes:

Council considered the recommendation made by Cabinet at its meeting held on 20 June 2018 relating to the budget for the design phase of the redevelopment of Thameside House.

 

Resolved to approve the capital expenditure budget of £3.75m for the design phase of the project for the redevelopment of Thameside House for 2018/19 - 2019/20.

 

 


Meeting: 20/06/2018 - Cabinet (Item 2500)

2500 Exempt report - Thameside House Construction Advisors and Design Team- Key Decision

Councillor I.T.E. Harvey

 

To consider a report seeking approval of the budget for the design phase of the Thameside House project to create a target of 120 new apartments. 

 

Reason for exemption

This report contains exempt information within the meaning of Part 1 of Schedule 12A to the Local Government Act 1972, as amended by the Local Government (Access to Information) Act 1985 and by the Local Government (Access to information) (Variation) Order 2006 Paragraph 3 – Information relating to the financial or business affairs of any particular person (including the authority holding that information) and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information because, disclosure to the public would prejudice the financial position of the authority in the bidding procurement of contracts by allowing other parties to know the position of the Council.  This in turn prejudices the Council by (i) distorting the procurement process and (ii) prejudicing the opportunity for the Council to place contracts for the prudent management of its financial affairs.

 

Additional documents:

Minutes:

Paragraph 3 – Information relating to the financial or business affairs of any particular person (including the authority holding that information)

 

Cabinet considered an exempt report seeking their recommendation to Council for an expenditure budget for 2018/19 to 2019/20 for the provision of a design team for the redevelopment of Thameside House, and delegated authority to be given to the Group Head of Regeneration and Growth in consultation with the portfolio holder to appoint the advisors and design team.

 

Alternative options considered and rejected:

To withhold approval resulting in the property remaining empty

 

Resolved:

1.    To recommend to Council that the capital expenditure budget for 2018/19 to 2019/20, as set out in the report, be approved.

2.    To authorise the Head of Corporate Governance to enter into any legal documentation necessary to implement the redevelopment project and

3.    To delegate the appointment of the advisors and design team to the Group Head of Regeneration and Growth in consultation with the Portfolio Holder.

 

Reasons for recommendation:

·         Redevelopment of existing offices on site to residential would regenerate a site which was becoming an eyesore for the town.

·         The ongoing revenue stream (once the works have been completed) will assist in the future long financial stability of the Council.