Eclipse Leisure Centre Additional Spend

20/01/2025 - Eclipse Leisure Centre Additional Spend

The Committee requested that a more clear and concise report be brought back to this committee for them to consider the current budget position for the construction of the Eclipse Leisure Centre.


08/01/2025 - Eclipse Leisure Centre Additional Spend

Committee resolved to:

 

1.     Approve option one and a budget of £3000 in relation to the sauna coals.

 

2.     Approve option 4, subject to exploring alternative hedging solutions and a budget of £10,000 in relation to the barrier to protect the turfed area.

 

3.     Delegate approval of the final solution in relation to the design barrier to protect the turfed area to the Group Head Community Wellbeing in consultation with the Chair and Vice Chair of Community Wellbeing and Housing Committee.