Provisional Capital Outturn Report 2019/20
Cabinet member: Cllr Sati Buttar
To receive the provisional capital outturn report for 2019/20.
Additional documents:
Minutes:
Cabinet considered a report on the provisional capital outturn spend for 2019/20.
The majority of the £153.7m underspend related to property development schemes and the remainder to Corporate ICT projects. The proposed capital carry forward of £76.5m included £76.4m for the development of Oast House and various other capital schemes.
Resolved to:
1. note the provisional capital outturn spend for 2019/20; and
2. approve the capital carry forward of £76,525,900.
125 Provisional Capital Outturn Report 2019/20 PDF 99 KB
To note the provisional capital outturn report for 2019/20 which will be considered by Cabinet at their meeting on 15 July.
Additional documents:
Minutes:
The Chief Finance Officer presented a report on the 2019/20 provisional capital outturn and responded to Committee members’ queries.
Members raised concerns about: the accuracy of future expenditure requirements, whether the Committee should review reasons for carry forward requests, the apparent inconsistency of such requests and the resulting difficulty in scrutinising the report. A member proposed that the Committee should include scrutiny of the Council’s project accounting in relation to the capital budget as part of its work programme.
Resolved to:
1. note the 2019/20 provisional capital outturn and the carry forwards totalling £76,525,900; and
2. propose that scrutiny of the Council’s project accounting in relation to the capital budget be included in the Committee’s work programme.